Look Aheads

Report of Upcoming Work

Week of the May 3, 2021

Section 1

There are two crews currently installing water main pipes in Section 1. At times crews will be working in different locations at the same time.

Crews are expected to install water main pipe and perform water main connections on the following streets:

  • Open cut pipe installation on Cardiff Street
  • Grading for sod on Sounding Drive, Sulstone Drive and 3600 block of Peace River Drive
  • Wireline testing in entire Section 1 contract area

Motorists can expect minor delays while crews progress with construction.

Section 2

No advisory at this time.

Section 3

No advisory at this time.